RadKod in numbers
Every year RadKod calculates from its own project panel how many projects and phases finished on the promised day, how long projects took and how many hours were logged, and publishes the results. The numbers are anonymous and go live after management approval.
In 2026, 3 of the 5 project phases we delivered finished on the promised day.
- Phases finished on time
- 60%
- Average delay of late phases
- 10.5 days
- Hours logged
- 167
- Tasks completed
- 5
- Clients we worked with
- 3
Source: real records in the RadKod project panel, anonymous totals. Approved by management: 2026-09-26.
How do we calculate this?
Every phase has a promised date written in the quote. A phase finished on or before that day counts as on time. A project is delivered when its last phase is finished. Cancelled work is excluded, and no client name appears anywhere.